Remote diagnostics can outlive the authorised repair
A mine may rely on several equipment manufacturers for crushers, pumps, fleet telemetry, ventilation and processing systems. Remote diagnostics help restore service, but emergency connectivity often accumulates over time: an old supplier tunnel stays enabled, a subcontractor inherits a shared credential, or a troubleshooting route reaches equipment unrelated to the original fault. A remote-access approval matrix should make these pathways visible and constrain them without delaying safety-critical maintenance.
The relevant unit of approval is the specific support activity, not a vendor’s company name. A request to inspect a condition-monitoring appliance should not automatically grant a route to every controller on the process network. Likewise, allowing read-only telemetry does not authorise firmware uploads, control changes or remote administration of the historian. Permissions must be proportionate to the asset, task and operational consequences.
This is a governance and assurance worksheet, not an instruction to connect to live industrial control devices. All discovery, configuration changes and testing must be approved by the site’s operational authority and conducted with appropriately qualified OT specialists. Where loss of communications could affect safety or plant stability, use design review, configuration inspection and offline simulation before considering any production verification.
Identify the actual support chain
Start with the mine’s supplier register, maintenance contracts and network diagrams, then confirm them with the maintenance superintendent and OT engineers. Include original equipment manufacturers, local service agents, managed security or network providers, instrumentation specialists and suppliers who connect through another vendor’s remote tool. A support ticket may name a multinational manufacturer while the actual session comes from an independent field contractor.
For each supported asset, capture the equipment identifier, site location, process owner, operational criticality, supplier contract, named technical sponsor, maintenance window and known connectivity mechanism. Distinguish a vendor cloud relay, site-to-site tunnel, brokered jump host, cellular modem, removable diagnostic laptop and on-site technician connection. These are different access paths, even if the user sees the same vendor logo in a portal.
Verify the inventory through authorised network records, supplier specifications and maintenance logs. Do not run active scanning against controllers merely to fill inventory gaps. Ask the OT engineer whether process historians, safety-related networks, engineering stations or remote telemetry units share upstream routes. An access rule that appears narrow in an IT firewall may still permit lateral movement through a dual-homed engineering workstation.
Build a matrix that separates ability from permission
Useful columns are request ID, supplier, nominated individual, sponsoring site employee, work order, asset or zone, entry mechanism, authentication method, privilege level, approved commands or functions, permitted source, start and end times, independent approver, session logging, revocation evidence and fallback contact. Add a field for what the supplier cannot access. An explicit exclusion can prevent ambiguity when a vendor has similar equipment in adjacent process areas.
Use different approval classes. Observation covers approved read-only diagnostics and log retrieval. Maintenance may allow configuration changes after operational controls are established. Safety-critical or high-impact work requires a formal change and risk process that examines physical consequences, vendor procedure and recovery arrangements. These categories are illustrative: align them with the actual site’s permit-to-work, electrical isolation and management-of-change processes rather than treating cyber approval as a replacement for industrial safety procedures.
Avoid indefinite standing access where practicable. A supplier may need recurring emergency support, but the entitlement can still require a site-authorised activation tied to a case number and an approved time window. Emergency access should be fast, traceable and reviewable, with a retrospective authorisation path if the business has formally designed one. “The vendor needs 24/7 support” is a service objective, not a justification for an unmonitored permanent route to every process subnet.
Walk through a planned pump-diagnostics request
Imagine a hydraulic pump reporting unstable pressure. The equipment supplier requests remote read access to the condition-monitoring server. The maintenance planner enters the fault and approved time; the OT engineer confirms the server is not a safety instrumented system and that no write operations are needed. Cyber operations validates the named engineer’s account, source location and brokered session path. A supervisor authorises the support connection within the site’s maintenance process.
Before activation, confirm the expected destination and approved diagnostic tools. The session should pass through the designated access broker or jump environment, not a generic VPN landing point with broad subnet routes. Capture the session identifier and ensure the monitoring approach respects operational and commercial sensitivity. If the requested change expands to controller parameters, pause and obtain the additional authorisation; a troubleshooting conversation is not permission to alter the process.
At the end, the site engineer confirms that the diagnostic task is complete, the supplier’s session is terminated and temporary entitlements are revoked. Check the broker and firewall logs against the recorded window. If the supplier maintains a persistent account for licensed software, record that distinction; disable interactive access while preserving the application’s legitimately required service identity. Otherwise an overzealous cleanup could interrupt plant operation.
Validate the exclusions without disturbing the plant
A good access matrix can show that the correct path opens, but its protective value depends on the paths that remain closed. Have an independent OT network reviewer inspect effective routes and device policies for connections to unrelated process cells, engineering workstations and safety-related systems. Where a safe lab replica exists, use a synthetic vendor identity to confirm that an observation entitlement cannot upload new configurations or reach a second equipment zone.
Do not use uncontrolled vulnerability scans, password guessing or disruptive traffic generation against production OT. NIST’s OT security guidance emphasises performance, reliability and safety requirements; these considerations should govern the test plan. If a production verification is necessary, scope it as a non-invasive connection to an agreed test endpoint and establish a stop condition, communications channel and responsible operator before execution.
Look for bypasses that policy documents may miss: vendor-provided cellular equipment outside site monitoring, old remote-desktop tools on engineering PCs, unmanaged maintenance laptops and direct cloud access embedded in instrumentation platforms. Decide how each is controlled or retired. A firewall deny is meaningless if a second modem provides a route around it.
Prepare for outages and contested sessions
A support channel can fail during a production incident. The matrix should say whether the mine can safely continue using local personnel, a phone-assisted diagnostic procedure or an approved alternative access broker. Record the vendor’s availability commitment but verify what the site can do when the external network is down. The fallback must not depend on someone sharing credentials through an unsecured chat or disabling protective network rules under pressure.
Add a short compromise tabletop. The site receives a credible alert that a vendor’s engineer account may be misused while a maintenance ticket is open. Who can suspend the specific session without disconnecting vital telemetry? Which logs demonstrate the last commands or destinations reached? Who checks whether the diagnostic work actually changed any production settings? Which physical operations continue safely while access is restricted?
A response should preserve relevant evidence and coordinate with process safety staff. Cyber operations cannot independently declare a plant safe because an account was disabled. Conversely, a request to keep production running should not conceal a suspected unauthorised modification. The site incident commander needs a defined way to balance those decisions and document the residual risk.
Audit approvals, exceptions and closure evidence
Sample past maintenance tickets. Match the authorised individual, time window, accessed asset, session record and actual closure. Mark gaps such as shared supplier identities, absent logs, unexplained extensions or access continuing after a contract change. Give each exception an owner, due date and compensating safeguard. Temporary unrestricted access should have an expiry and be reconsidered before renewal, not silently become routine.
Procurement and contracts need a role. New supplier agreements should specify approved connection methods, identity ownership, subcontractor notification, logging, incident cooperation, credential revocation and support for safe technology upgrades. Check how a supplier handles personnel departures. A central vendor portal may claim that a user is disabled while the person’s site VPN account remains active.
Finally, give the maintenance superintendent a concise operational summary: which vendors can connect to what, what safety constraints apply, how support is activated, and whom to call when the normal method is unavailable. Give cyber operations a more detailed access-control and log-evidence record. Both need the same current asset and entitlement identifiers, even if their interfaces differ.
Inspect change drift after emergency work
An after-hours repair may leave temporary vendor routes that no one remembers to remove. Schedule a review of remote-access changes against completed maintenance orders, especially after an unplanned shutdown or equipment warranty visit. The reviewer should compare the approved destination and session period with the effective firewall and broker policy still in force. A change ticket marked “closed” is not proof that the technical exception expired.
Use a weekly exception report for active temporary entitlements and a periodic independent sample of older service accounts. Include inactive suppliers whose contracts have ended but whose gateway objects remain. If a vendor equipment upgrade introduced a new cloud relay, record the resulting traffic path and decide whether it falls within the existing authorisation. The site may legitimately accept a revised connection architecture, but the acceptance needs a new hazard and cyber assessment rather than being treated as a minor endpoint change.
Give the site manager a practical escalation route for urgent cyber concerns discovered during maintenance: preserve logs, stop only the relevant access where safe, inform the operational controller and obtain an approved remediation plan. The aim is to make unusual access visible without encouraging IT teams to issue sudden commands to industrial equipment.
Accept the design on evidence, not familiarity
Completion should require an approved inventory of remote routes, named human ownership, tested revocation and a sample of correctly scoped sessions. Test whether one vendor’s credentials can traverse an unrelated process zone using an approved non-invasive method or documented policy proof. Require a new sign-off after major equipment replacement, network integration, outsourcing changes or emergency rule additions.
The best result is neither unrestricted connectivity nor a blanket ban on remote support. It is reliable diagnostic access that begins with an authorised maintenance need, stays within an identifiable equipment boundary and closes without leaving an unexplained network pathway behind.