Turn Secure by Demand Into Acceptance Tests for Manufacturing OT

Use the January 2025 joint OT procurement guidance to compare products on operating consequences, verifiable controls and long-term supplier support.

In January 2025, CISA and its international partners published Secure by Demand guidance for operational technology owners and operators. ASD and New Zealand’s National Cyber Security Centre published their guidance pages on 14 January. The joint guidance asks buyers to assess security when selecting digital products used in industrial environments. For a manufacturer replacing a controller, an engineering workstation or a supervisory application, the immediate question is what evidence it can require before purchase and what it must still verify at acceptance. The answer should account for the service life, operating constraints and authority the product will introduce.

Start with what the equipment can affect

Ask the plant and engineering owners to describe the proposed product’s function and its failure consequences. Identify where it will be installed, who can configure it and which people or services depend on it. A product that collects routine status information presents different operating consequences from one that can modify production or safety-related settings. Consider the role of maintenance and supplier support alongside ordinary operation. Identify which existing equipment, data exchanges and recovery arrangements the new product must work with.

Put the critical requirements into a buyer’s record. Examples include a means of controlling engineering access, event evidence for configuration changes, a supported way to restore approved settings and a documented maintenance path. Link each requirement to a responsible owner and the consequence of a failure. The joint guidance addresses several product security considerations, including logging, configuration management, authentication, secure defaults and upgrade tooling. Use the categories to identify evidence needed for the specific purchase. A low-consequence device and a supervisory system need different demonstrations and priorities.

Compare the product you would receive

Ask bidders to state which security functions are available in the product baseline, which depend on extra components or licensing and which are planned for a later version. Give them the same configuration and operating scenario. Ask what the customer can verify locally and what requires a supplier account or hosted service. Document the supported version and operating assumptions. A capability shown in a different product line or demonstration environment may not be present in the equipment the plant will accept.

Require a representative demonstration in an approved environment. For access control, ask the supplier to use fictional roles to show what an operator, engineer and approved support person can do. Verify that a person without the required authority cannot make the protected change through ordinary product features. For logging, ask the supplier to show the event generated for an approved configuration change, identify its actor and time, and explain how the site can retrieve it. Record whether the evidence remains available when the supplier cannot be reached. A dated observation is more useful than a box marked supported.

Make support and update arrangements part of the purchase

Ask how the supplier communicates security issues, supports updates and identifies the versions in scope. Request an example notice and ask which information the customer can use to verify whether its product is affected. Confirm the expected support period, the release approval process and the conditions for a customer to test or postpone an update. Determine who can obtain the approved release and how its integrity is confirmed. If a supplier needs remote access to assist, agree the named role, approval, time limit and evidence for the session.

Test a failed or deferred change during a representative maintenance window. The plant should be able to explain which operation can continue, what authority is needed and how it would return to the approved state. Ask the supplier which settings or licences are necessary for recovery and whether the customer can obtain them independently. If an older configuration would reintroduce an unwanted access path, require the recovery plan to account for it. Record which parts can be tested before installation and which must be verified at site acceptance under approved conditions.

Decide what trade-offs the plant can accept

An inexpensive product might meet the immediate engineering need and require more support work or a separate control throughout its life. A product with stronger built-in protections might need an integration change or a different maintenance schedule. Compare these effects over the expected service life, including the people and evidence needed for operations. Ask the purchasing team to show the expected total operating effort and the consequence of a missing control. A trade-off should identify which requirement is being accepted, who owns the decision and what evidence would justify revisiting it.

Set mandatory acceptance conditions for material operating risks. For example, the plant may need a verified way to withdraw supplier authority, a usable configuration record and a tested recovery route before the product is used in an essential service. Where a product cannot meet a requirement, consider whether an alternative control can be demonstrated safely and maintained by the site. Give any exception scope, expiry and an owner. Keep an unsupported claim or future feature visible as an open condition. The buyer can then distinguish a deliberate choice from an assumption that a supplier will solve the issue after installation.

Carry the evidence into factory and site acceptance

Write acceptance tests before committing to the purchase. Name the product and version, expected observation, approved environment and independent reviewer. Include an ordinary operating task and a restricted action. Verify the evidence can be retrieved by the people who will need it. Ask the supplier to demonstrate a configuration backup and a representative recovery under approved conditions. Have the plant owner verify the business or operating result. Note which conditions differ between a factory test and the installed site and assign a separate test where necessary.

Keep a record of exceptions, supplier commitments and review dates. Make the ownership and evidence provisions usable during a shift or maintenance window. Ask a new duty person to find the approved supplier contact and explain how an access grant would be stopped or verified. If the instructions rely on a project team member or supplier portal, test an alternative. NIST’s OT security guide emphasises considering safety, reliability and performance. The acceptance process should show how the plant will meet those constraints as it verifies security.

Ask leaders to review the next decision, with evidence

Report the most consequential product differences, tested conditions and outstanding commitments. Measure whether bidders demonstrated the mandatory controls, how many site checks remain open and when the next supported update or review is due. Give the board or procurement sponsor a clear decision about the service impact and evidence. At renewal or a material product change, repeat the most important checks. Secure by Demand is useful when the manufacturer’s expectations show up in the purchase, the installed product and the records the plant can rely on later.

Bring the supplier’s next product update into the review. Ask whether the change affects logging, access or recovery evidence. Confirm the authorised people can still perform an ordinary task and obtain the expected records. Document any requirement the product now meets or no longer demonstrates, then give the resulting decision a named owner.

A useful purchasing record survives personnel changes. Store the accepted configuration, test results and supplier obligations together so a new engineering owner can check what was bought.

Retain the review date.

Make the OT purchase decision depend on verifiable product behaviour

For a proposed controller or gateway, request the configuration available at delivery rather than relying on a future security roadmap. Include default account handling, remote-support disablement, firmware verification and the supplier’s process for disclosing vulnerabilities in the purchase assessment. During a factory acceptance session, use a spare device to show how a maintenance identity is created, restricted and revoked; a sales slide is not substitute evidence. The buyer should also ask whether diagnostic access persists after a communications outage and which settings are lost during a factory reset. Record any dependency on proprietary software or a remote vendor service that could affect restoration during an incident. If a safety-critical function cannot accept an immediate update, document the compensating separation and the approved review date. That makes a procurement exception visible to engineering and cyber teams before the plant inherits it.

Sources and further reading

Strengthen your security with Next Defence

Next Defence can help manufacturers translate OT procurement requirements into evidence, contract commitments and site acceptance tests.

Explore OT, IoT & Critical Infrastructure Security ↗

LET'S TALK

Let’s talk about your security.

Tell us what you are protecting, where you need greater visibility or what you want to achieve. We will help identify the right next step.

Talk to a Security Specialist

Describe your security requirements. Please do not submit passwords, credentials or confidential incident evidence. This form is not an emergency incident-response channel.

Form powered by HubSpot. Review our Privacy Policy. If the form doesn’t load, email [email protected].