An assessor proposes scanning a manufacturing maintenance gateway to check whether its security configuration is sound. The gateway also connects to engineering workstations and fragile operational equipment. Without a defined exclusion, a routine enterprise scan could touch an industrial controller that reacts unpredictably to unexpected traffic. This workshop pack puts plant ownership, safe scope, evidence needs and stop authority ahead of any technical activity.
The test authorisation is the first deliverable
Invite the plant safety lead, operations supervisor, OT engineer, cybersecurity assessment lead, vendor representative and maintenance planner. Establish exactly which business question is being answered: for example, whether contractor identities are restricted to the maintenance jump host and authorised diagnostic functions. Do not approve “scan OT” as a test objective. State the desired evidence as a bounded routing and permission decision with a defined source and destination.
Choose a supervised read-only diagnostic in a lab replica as the permitted action. Name the unacceptable action: a scan, configuration write or unexpected session reaches a controller outside the agreed scope and disrupts production equipment. An authorisation that mentions the gateway IP address but ignores its downstream connections is incomplete. Include intermediate hosts, NAT, vendor tunnels and secondary management paths.
The scope statement should contain the tested assets or replicas, protocol families, approved methods, windows, rate limits if appropriate, exclusions, evidence storage, escalation numbers, expected service behaviour, preconditions and the individual authorised to order an immediate halt. Any use of actual plant assets requires a separate operator-approved risk and safety assessment; a signed cybersecurity form cannot override operational safety.
Map the gateway’s downstream reach
Use existing engineering drawings, approved configuration, passive network records and interviews to build a route map. Show where the assessor’s identity is converted to a shared vendor account or workstation session. Record destinations by zone and equipment function without distributing the full sensitive topology outside the approved team. Determine whether ordinary IT discovery probes could transit a forwarding rule to controller networks.
Check which components share the maintenance gateway: packaging cells, refrigeration, process instrumentation, building services or remote OEM tools. One connection may support a running production warranty task while another is dormant. The sponsor needs that distinction before changing firewall policy or revoking credentials. Record what monitoring is available to observe any unwanted traffic.
Confirm safe recovery prerequisites: a trusted copy of the gateway configuration, a valid console or out-of-band management route, current contacts for the equipment supplier and a path to restore ordinary maintenance access. A test should not begin when the team cannot explain how to abort it or how to recognise a production-side effect.
Workshop scenario 1: scope ambiguity
The facilitator gives participants an assessment statement reading “scan the maintenance gateway and connected systems for vulnerabilities”. Ask each role to identify a phrase that could enable unsafe activity. The plant engineer should list excluded equipment; the cybersecurity lead should narrow the technical method; the vendor should identify tool behaviour; operations should identify the production window and alarm conditions. Rewrite the statement so it specifies a passive evidence review plus a lab-based identity and routing test.
The completed decision must distinguish what is authorised now from what would require a later change request. “No known issues” is not a justification to run a test outside the agreed boundary. If the vendor cannot describe a tool’s probe set, the tool is not approved simply because it is common in office IT.
Workshop scenario 2: an unexpected forwarded path
In a representative lab, the test support account connects to the gateway and attempts to reach the approved simulator of an engineering workstation. That route may succeed if the work order permits it. The account then requests a simulated destination in another zone. Observe the gateway’s actual refusal, the source and destination and the event identifier. The exercise must not send the equivalent packet to production machinery.
If the simulator reveals that the gateway forwards all traffic to a privileged workstation, record a boundary defect. The corrective action might involve a narrower jump-host role, specific route filtering, separate vendor sessions or an engineering-controlled access broker. The fix should be tested for the correct diagnostic function as well as the forbidden cross-zone action. Security is not improved if plant personnel lose the approved maintenance path and must invent an uncontrolled alternative.
Workshop scenario 3: a technician requests a write
Introduce a fictional vendor engineer who says a quick remote parameter change is necessary to restore an alarm. Ask what evidence establishes approval: equipment ID, safe state, work order, qualified engineering authority, permitted change, time window and rollback. A general gateway login is not enough. In the lab the team should show that a diagnostic identity cannot issue the simulated write. A separately approved maintenance identity may perform a controlled change only through the plant’s documented procedure.
Do not conduct a write or stress test on live industrial controllers under this workshop. Any future production change needs its own method statement and safety approval. The workshop’s purpose is verifying that technical access does not quietly bypass the engineering decision.
Workshop scenario 4: monitoring reports a side effect
During the simulated assessment, the facilitator announces increased gateway latency and a controller simulator alarm. The observer should activate the stop procedure without waiting for proof of causation. Record when the anomaly began, which test was running, whether it stopped, who was informed and what evidence was preserved. Only the operations lead can authorise a restart after checking the representative plant state.
Ask the team to distinguish three explanations: the test caused the change, an unrelated maintenance task overlapped, or telemetry itself is faulty. Retain event IDs and clocks that enable later comparison. Do not assert that every nearby alarm was caused by the assessment. If safe continuation is impossible, close the exercise and mark the relevant case not demonstrated.
Workshop scenario 5: the normal vendor route is unavailable
Simulate an identity-provider outage during a genuine maintenance window. Does the plant have a supervised and attributable emergency access route? Who authorises it? Does it use a standing shared password with no expiry, or a recorded procedure with restricted reach? Check the recovery route in the lab, then test that the emergency permission is removed after the exercise. A fallback that remains perpetually broad is a separate risk requiring an owner and review date.
The plant safety lead should decide whether maintenance may be deferred until normal identity services return. The exercise does not presume that availability always outweighs access control or vice versa. Record how the decision changes for safety-critical versus routine diagnostic work.
Rules of engagement checklist
Before testing, obtain a scope diagram approved by engineering, inventory of exclusions, authorised identities, methods and tools, test timing, evidence-handling plan, communication channel, response contacts, stop signals and rollback prerequisites. The assessor should demonstrate that the tool configuration matches the approval and that personnel can observe the intended boundary. Any change to target, technique or rate requires a new approval, not a verbal interpretation after work begins.
During the test, keep a signed activity log: method, start/stop time, source account, permitted destination, observed behaviour and resulting evidence identifier. The observer should be able to halt the activity without seeking permission from the assessor. Retain configuration files and synthetic test results securely. Where service or safety implications prevent a test, substitute a documented lab assessment and state precisely which production characteristic remains unverified.
After testing, reconcile observed traffic with the approved route map, review monitoring anomalies, verify the legitimate support function and close temporary accounts or firewall openings. Any session that survived the expiry is a failed revocation case. Place defects into the plant’s managed change process rather than leaving a general “security improvement” recommendation with no engineering owner.
A pass/fail record that operators can use
Give every workshop case a unique identifier, authorised objective, excluded activity, environment, tester, operational observer, expected result, actual result, log evidence, incident/stop outcome and accountable approver. Use pass when the expected safe behaviour was witnessed, fail when the protective boundary did not operate, and not demonstrated when the case could not be evaluated. Do not convert a written policy into a passing technical result.
The final workshop output should be an approved testing boundary, agreed safe methods, a tested abort and rollback route, an access decision for the permitted diagnostic and a list of unresolved hazards. The assessor should know exactly what not to do, and the plant operator should know which evidence justified the approval. A careful lab-based finding is more valuable than an extensive production scan whose operational consequences nobody owned.
Hand the findings to the next maintenance shift
Include the night-shift supervisor in the closeout. Ask them to find the approved gateway route, the exclusions and the emergency stop contact without assistance from the assessor. If the next shift cannot locate an exception or cannot identify which vendor session is still active, the workshop did not achieve an operational handover. Attach a concise change summary to the plant’s normal maintenance record, including the temporary rules to withdraw, expiry time and person who will confirm withdrawal. Revisit the rules of engagement when a new line, engineering station or remote support partner changes the downstream route.
Sources and further reading
Explore Next Defence expertise
Next Defence can help your team evaluate the permissions and operational risks in ot security test approvals: a manufacturing workshop pack. Our specialists can review evidence such as Rules of engagement, test diagram, maintenance plan, passive logs and stop conditions, assess whether the authorised work remains usable, and test controls against the unacceptable case where the assessor’s scan or command disrupts production equipment outside approved scope. We can agree proportionate remediation with plant safety lead and ot assessment manager, backed by a repeatable acceptance test and clear incident responsibilities.