A complete-looking spreadsheet can hide the unknowns
A utility combines engineering drawings, historic vendor spreadsheets and passive network observations into one operational technology inventory. Devices now appear in neat rows with make, model, firmware and site location. The problem is that some values were copied from a five-year-old diagram, others inferred from traffic and still others confirmed by the current site engineer. A single ‘complete’ indicator conceals those differences and can send an incident team toward the wrong equipment.
Asset identity is an evidence problem. Two gateways may share a naming convention, one device may have been replaced without an address change and a controller’s firmware may not be observable from normal network telemetry. If an inventory cannot explain where each important assertion came from, neither vulnerability triage nor emergency isolation can rely on it with confidence.
Record provenance at the field level
For critical assets, collect the tag, function, site or zone, network path, manufacturer, model, software or firmware, owner, maintainer and dependency on other systems. Add source, observation date and confidence to values that could change a response decision. ‘Firmware verified by supervised console read on 12 August’ is materially different from ‘firmware copied from tender schedule’. Do not force both into one unqualified value.
A useful confidence scheme might distinguish directly verified, corroborated from independent evidence, inferred and unknown. Define who can upgrade the label and what proof is required. Confidence is not an assurance that a component is secure; it tells the next reviewer how much trust to place in a specific inventory claim. Keep contradictory evidence visible until an authorised person resolves it.
Treat connectivity and authority as inventory fields
An OT register that lists devices but omits network conduits cannot support meaningful containment. Map the communication relationships that matter: engineering workstation to controller, vendor remote support to jump host, telemetry collector to station and historian to reporting platform. Record the business purpose of each route and the team able to approve its removal. The fact that a gateway is ‘internal’ says little if a contractor can reach it through an older remote-access path.
Avoid aggressive scanning where equipment safety or vendor support may be affected. Passive observations can reveal hosts and protocols but may miss powered-off spares, serial connections, infrequent control actions and maintenance access used only during shutdowns. Pair them with engineering documents, procurement information and supervised operator confirmation. State explicitly which categories the discovery method cannot find.
Build an evidence-led reconciliation cycle
Start with a representative treatment site and select the assets whose loss would interrupt safe operation. Compare the latest engineering drawing with switch port records, passive telemetry, vendor service tickets and an authorised on-site check. Investigate mismatches before merging identifiers. Preserve the original source so an engineer can reverse an incorrect correction later.
Use controlled change events to update the register: replacement of an RTU, supplier gateway upgrade, temporary maintenance laptop, changed SIM or new remote-access route. Capture the person approving the change and the evidence that it took effect. A register updated only during the annual audit is most likely to be wrong when an emergency follows a recent engineering project.
A safe test of an uncertain record
Suppose a gateway is shown as using an old firmware release in a vendor spreadsheet, while passive traffic suggests a newer device family. Do not schedule a production patch based only on either clue. Ask the responsible engineer to verify the physical label, management information or vendor-provided attestation through a permitted method, recording any maintenance restriction. Meanwhile, the vulnerability ticket can remain ‘applicability unresolved’ with a named owner.
Repeat the test for an access route. If the inventory says a supplier VPN was retired, inspect the authorised network configuration and access logs to determine whether the path remains enabled. A successful denial from the enforcing system is more persuasive than a closure note in a project tracker. Use a controlled test identity and written scope; no probing of safety-critical controllers should be inferred from this advice.
Give the incident team useful choices
In a suspected compromise, responders should be able to identify which system the asset controls, which other services would fail if isolated, whether a trusted local operator is available and which evidence can be collected without disrupting safety functions. Unknown firmware is one issue; unknown operational consequence is another. A high-confidence component name cannot substitute for a site-approved response sequence.
A good risk report distinguishes confirmed devices, conflicting records, unverified dependencies and genuinely unobserved network segments. Assign dates and owners to the significant unknowns and highlight where temporary restrictions can reduce exposure until verification is possible. Do not translate missing inventory into an unsupported count of secure assets.
What to measure after the initial cleanup
Track critical fields verified within a defined period, unresolved conflicts that affect incident decisions, assets without a business owner and remote-access routes not linked to a legitimate maintenance need. Report these as proportions of a known scope rather than as percentages of an unknown estate. Recheck confidence after major vendor, firmware and network changes.
The inventory is valuable when it helps engineering and security decide where a change is safe, what is truly exposed and who has authority to act. Confidence labels turn a polished spreadsheet into a more honest operational map.
Example: three records describing one gateway
An old engineering drawing identifies a telemetry gateway as Model A at Site 4. A vendor maintenance worksheet uses Model B and a newer firmware number; the passive collector sees the same management address as before. The three records cannot simply be merged into a ‘latest known’ truth. The network address may have been reused after replacement, the vendor sheet may refer to a spare and the passive fingerprint may be incomplete. Assign a provisional asset identifier and preserve all observations with their collection dates.
A supervised on-site check can reconcile the equipment tag, serial number and authorised firmware evidence. The engineer should confirm which process the unit serves and where a fault would be visible. If the physical device cannot be accessed until the next shutdown, mark the disputed details as unverified and consider temporary network restrictions that do not jeopardise operation. Do not create a false assertion of certainty to satisfy a vulnerability-reporting deadline.
How to avoid making inventory maintenance another safety risk
Asset discovery tools vary in how they interact with devices. Even a lightweight active query can be problematic for unsupported controllers or constrained serial-to-IP gateways. Establish a method approval register, listing permitted passive sources, supplier-approved diagnostic commands and test windows. A device absent from active scanning may be an intentionally isolated controller, not an unused asset. Record the reason for exclusion and identify a non-invasive verification route.
Also distinguish equipment ownership from data stewardship. A maintenance contractor might know firmware versions; the utility remains responsible for the operational register. The network team may own switch information but cannot attest to process safety. Assign each disputed field to the person with the relevant authority, and make reconciled evidence available to emergency responders without exposing a sensitive network map more broadly than required.
Turn confidence into an escalation rule
If the inventory shows a critical remotely reachable device with unknown firmware, do not automatically treat the vulnerability as confirmed. Escalate for verification based on the consequence and plausibility of exposure. If an isolated spare has the same uncertainty, plan a lower-urgency check. Both unknowns deserve owners; their urgency differs. This is where confidence information becomes an operational prioritisation tool rather than a decorative spreadsheet column.
Capture uncertainty as a decision that can be revisited
For one high-consequence gateway, create a short confidence record containing the value being asserted, its evidence source, the date it was checked and the custodian who can resolve a disagreement. For example, a firmware version copied from a supplier spreadsheet is provisional until an authorised engineer checks it against an offline configuration export or another site-approved source. A packet capture may confirm the gateway is communicating without proving the hardware serial number or current patch level. Keep those confidence ratings separate instead of averaging them into an apparently precise asset score.
At the next maintenance window, ask the engineering owner to close one disagreement and record what changed in the incident playbook. If the mismatch persists, the response instruction should say what to avoid and who can provide authoritative identification before a containment action. An unresolved entry is not a failed inventory exercise when the uncertainty is visible and safely owned.
Sources and further reading
How Next Defence can help
Next Defence can help engineering teams assign evidence confidence to OT inventory records and select non-disruptive validation methods.