Exercise objective: sever an enterprise route without losing safe control
An electricity utility needs to contain a suspected compromise in its corporate network while retaining fault alarms, engineering telemetry and authorised control-room visibility for substations. A network boundary that looks clean on a diagram may also carry dependencies such as time synchronisation, message brokers, remote engineering sessions or vendor monitoring. This rehearsal uses an isolated simulation of an electric control-room environment, not a live transmission or distribution system. Its purpose is to establish which connections can be blocked promptly, which require engineering sequencing, and what evidence proves safety-critical services continue. The plant safety authority must approve all assumptions and stop conditions before the exercise begins.
Define a fictional network with an enterprise identity service, a demilitarised data exchange zone, a control-room SCADA display, two substation telemetry simulators and a historical reporting server. The control-room operator needs current alarm state and status messages; the corporate reporting team needs delayed operational summaries, but not a path to issue field commands. Place an artificial suspect corporate endpoint outside the OT boundary. The challenge is to isolate the suspect route while preserving the defined operational messages. Use synthetic tags that cannot command actual equipment. The engineering lead, network lead, SOC analyst and duty controller must agree on expected message timing and how they will recognise a dangerous side effect.
Produce a dependency map from observed flows
List the exact source, destination, protocol, purpose and owner of each cross-boundary flow. Include DNS, NTP, certificate validation, identity authentication, historian replication, remote maintenance, alarm transport and backup communications where present. Obtain evidence from approved network configuration and passive records rather than performing intrusive discovery on live controllers. Mark each dependency as essential for safe operation, deferrable, or unjustified in the selected response scenario. The control-room representative determines the operational importance of an alarm path; the security engineer cannot infer it solely from port number or traffic volume.
Test whether the engineering workstation receives time and identity information through the same corporate route that is proposed for shutdown. A design may contain a local time source but the application still depends on external certificate validation during session establishment. If the connection fails, an operator might be locked out during a fault. The rehearsal should verify such assumptions in the test estate by measuring actual alarm updates and the ability to use an authorised local control-room account. Record which dependencies are proven by observation and which remain vendor claims. Unknown dependencies are reasons for a staged response plan, not for risky experimentation on production devices.
Establish an alarm and telemetry baseline
Before introducing any isolation rule, generate synthetic normal, warning and critical substation messages with known identifiers and timestamps. Confirm that the control-room interface displays them within the agreed test interval and that operators can acknowledge and retrieve the associated event history. Record not only a network reachability check but the application-layer result. A firewall test that leaves TCP sessions connected while the alarm broker stops delivering new messages is a failure. Check historian values separately; delayed historical data may be tolerable while missing critical alarms is not. Engineering owns the threshold for each signal class and whether local fallback meets safe operating requirements.
Also rehearse a failed primary telemetry route with an authorised alternate path where the design includes one. Confirm that the alternate delivers correct tag identity and alarm severity, rather than merely connecting to the network. The exercise controller injects a distinctive synthetic alarm so its origin can be proven at the receiving display. If messages arrive out of order, the historian or alarm application must handle them according to the documented operational rule. Capture pre-change and post-change latency, message loss and operator visibility. A successful simulator test establishes confidence in the design but does not itself authorise the same action on live plant.
Trial containment in three ordered stages
Stage one uses the test environment to deny the suspect corporate host access to the exchange zone while legitimate telemetry remains active. Confirm the denied request at the firewall and at the target service, and verify that no alternate route permits the same prohibited access. Stage two simulates isolation of the wider corporate segment, using the approved path that preserves required operational dependencies. Check local authentication, alarm handling and safe control-room operation throughout. Stage three reintroduces permitted enterprise reporting through a narrow approved service route after the simulated incident is contained. Each stage needs a pre-authorised rollback condition and a named person who can stop it.
A stop rule is reached if a synthetic critical alarm is not displayed within the engineering-approved interval, if the operator loses required visibility, if a simulated control command is accepted from the corporate zone, or if test traffic escapes into live operational networks. The incident controller must halt the scenario and preserve configuration snapshots and logs. Do not override the stop rule to obtain a “complete” test score. The objective is to discover unsafe assumptions before a real incident, not to finish a scripted demo. Network changes in production require separate safety change management and the utility’s approved operating authority.
Test remote engineering and vendor bypass routes
A controlled architecture may have a vendor jump host or emergency maintenance gateway that was not included in the original incident diagram. Examine whether it can reach the same substations after the main corporate route is blocked. Use a synthetic contractor account and verify that the gateway denies an unauthorised site, user or command. Record the source of its access approval, session expiry and operator oversight. A legitimate remote engineer might need a short, local maintenance window during a corporate incident, but such access should have its own authority and scope. Avoid assuming that corporate directory deactivation instantly revokes a locally cached vendor credential.
Include a negative test for stale access. Expire a contractor’s synthetic work permit and attempt to reconnect to the lab gateway after central connectivity is withdrawn. Confirm the gateway applies the local expiry and records the denial. Test a permitted diagnostic read to establish that the restrictions do not eliminate necessary maintenance capability. If the gateway supports only broad access, the security team must propose an engineering-approved compensating pathway or defer the remote work. Do not convert a security incident into a hazardous plant intervention by demanding a rushed controller firmware update or indiscriminate scan.
Record evidence on both sides of the boundary
The network team captures configuration diffs, connection attempts and route decisions. The control-room team captures screen or simulator logs of synthetic alarms and operator acknowledgements. The SOC captures identity and gateway records, with an explanation of any log-forwarding delay. These artefacts should share stable test identifiers but need not depend on an always-on link to the enterprise SIEM. Confirm that buffered OT logs survive a simulated enterprise outage and can be reconciled afterward. Retain only the minimum operational detail required for review, with access restrictions appropriate to the sensitivity of the utility’s architecture.
A reviewer should be able to reconstruct when the containment rule took effect, which streams continued, which were interrupted deliberately, who approved the change and what prompted rollback or restoration. Do not treat an empty alarm screen as proof of normal operation; the test must generate known alarm events. A chart of network traffic volume is likewise insufficient to prove that control-room functions were preserved. The handover record should explicitly distinguish no observed loss in the simulator, a known dependency not covered by testing, and residual risks requiring a live operational procedure. These findings drive the safety review rather than a binary “network isolated” report.
Restore in a controlled order and sign off the limitations
After the simulated containment ends, restore only the routes approved for the current architecture. Confirm that devices do not reconnect through stale permissive rules and that queued reports do not flood the control-room data exchange. Test the same synthetic alarms and normal historian updates used for the baseline, then verify that monitoring and time synchronisation behave as expected. Record the recovered configuration identifier and the person who validated it. A staged reconnection should not bypass the change-control gate merely because it happens during an incident exercise. Define a method for preserving evidence if a live investigation later requires a longer isolation period.
The engineering authority signs safety and availability findings; the network owner signs route enforcement and reversibility; the SOC signs detection and event correlation; the business resilience lead signs the operational decision procedure. A result is accepted only when the team can explain which enterprise connections may be denied, which cannot be altered without local control-room approval, and how an unsafe side effect would be detected. Retest after SCADA upgrades, new vendor support arrangements, substantial routing changes or the introduction of new substations. The value is a safe, witnessed isolation capability, not a generic declaration that IT and OT are segmented.
Sources and further reading
Explore Next Defence expertise
Next Defence can help organisations assess the technical and business exposure examined in ot network isolation rehearsal for an electric utility control room. Our team can review the available source records, test the relevant access or operational controls and work with accountable owners to deliver plant-approved isolation scorecard with positive alarm and negative supplier-route tests.